According to article 8.2 of standard NF C 17-102:2011:

External protection against lightning using a lightning rod must be checked every year and after each lightning strike to ensure that it is functioning properly.

After an inspection, it is imperative to immediately correct any defects found in order to maintain optimal efficiency.

1- Verifications according to standard NFC 17-102: 2011

Verification periodicity relating to the level of protection
Protection LevelVisual Verification (year)Full Verification (year)Complete Verification of Critical Systems (year)
I and II121
III and IV241

A verification of your IEPF must be carried out within the
following cases:

  • Initially, upon completion of the IEPF,
  • Periodically (at least every 12 months),
  • Each time the protected structure is modified or repaired,
  • When the facility was struck by lightning.

 

Each periodic audit must be documented with a detailed report detailing all audit results and corrective actions to be taken.

For better monitoring and the extension of your warranty, create your verification file in the LPS Manager application.

LPS Manager - Verification Reports - Lightning Protection Installations

Your verification reports in LPS Manager

  • Compliance with the NFC 17-102: 2011 standard
  • Extension of your product warranty

2- Remote communication option, prevention, diagnostics and real-time monitoring

For the sake of prevention, to facilitate verification and maintenance operations imposed by the NFC 17-102:2011 standard and to extend your guarantees, LPS France recommends the use of the Contact@ir ® System* communication option.

Diagnostics:

This easy-to-use device allows you to carry out the diagnosis of your lightning protection installation remotely (in all the cases mentioned in paragraph 1 as at any other time) and to limit physical checks to cases of absolute necessity.

Real-time tracking**:

An alert is issued each time your lightning protection installation is hit by lightning and makes its immediate diagnosis possible.

* Contact@ir ® System is an LPS France exclusive. Sold separately.
**Depending on the Contact@ir ® System option level chosen.

Communication solutions for lightning protection systems - connected maintenance of early streamer emitter lightning rods and grounding of installations

Communication solution Contact@ir ® System

  • Compliance with the NFC 17-102: 2011 standard
  • Extension of your product warranty
English