According to article 8.2 of standard NF C 17-102:2011:

An external lightning protection system using a lightning rod must be checked annually and after each lightning strike to ensure it is functioning correctly.

After an inspection, it is imperative to immediately correct all defects found in order to maintain optimal efficiency.

1- Verifications according to standard NFC 17-102: 2011

Frequency of verification related to the level of protection
Protection LevelVisual Inspection (year)Complete Verification (year)Complete Verification of Critical Systems (year)
I and II121
III and IV241

A verification of your IEPF must be carried out within the
The following cases:

  • Initially, upon completion of the IEPF,
  • Periodically (at least every 12 months),
  • Each time the protected structure is modified or repaired,
  • When the facility was struck by lightning.

 

Each periodic verification must be recorded with a detailed report stating all the results of the verification and the corrective actions to be taken.

For better tracking and extension of your warranty, create your verification file in the LPS Manager application.

LPS Manager - Verification Reports - Lightning Protection Installations

Your audit reports in LPS Manager

  • Compliance with the NFC 17-102: 2011 standard
  • Extension of your product warranty

2- Option for remote communication, prevention, diagnostics and real-time monitoring

For prevention purposes, to facilitate the verification and maintenance operations required by the NFC 17-102:2011 standard and to extend your warranties, LPS France recommends the use of the Contact@ir® System* communication option.

Diagnostics:

This easy-to-use device allows you to diagnose your lightning protection installation remotely (in all the cases mentioned in paragraph 1 as well as at any other time) and to limit physical checks to cases of absolute necessity.

Real-time tracking**:

An alert is issued each time your lightning protection system is struck by lightning, making immediate diagnosis possible.

* Contact@ir® System is exclusive LPS France. Sold separately.
**Depending on the Contact@ir® System option level chosen.

Communication solutions for lightning protection systems - connected maintenance of early streamer emitter lightning rods and grounding of installations

Communication solution Contact@ir® System

  • Compliance with the NFC 17-102: 2011 standard
  • Extension of your product warranty